Aloha Stadium Demolition Wraps Up Early in Halawa |
Only the end zone structures remain as the developer plans a groundbreaking for the new stadium in early 2027 |

The view along Kamehameha Highway in Halawa looks very different now.
Demolition of the 52-year-old Aloha Stadium wrapped up earlier this month, well ahead of the end-of-year schedule, Hawaii News Now reported.
Work began in February with the explosive tripping of the east and west bleachers, followed by excavators cutting apart about 17,000 tons of steel.
"All the steel's gone. The field, the goal posts, all that stuff's gone," stadium manager Michael Yadao told Aloha State Daily after the Aloha Stadium Authority met Thursday, Nov. 19.
"It's just concrete right now in the northern and southern end zones," he said.
Finished early, and safely
Justin Lui, vice president for development at master developer Stanford Carr Development, said the job finished ahead of schedule and without injuries.
"Not only coming in ahead of time, ahead of schedule, but a safe job as well, so everyone can go home to their families," Lui said.
Crews worked to keep dust, noise and traffic disruptions down for neighbors, he said.
"We wanted to thank the community for supporting us," Lui said.
What's left standing
The concrete structures in both end zones were kept on purpose, a move the development team, Aloha Hālawa District Partners, expects to save about $90 million in demolition costs.
The spaces under the end zone stands have been gutted, and the developer expects the Hawaii Sports Hall of Fame museum to fit under the south end zone.
A pile of about 10,000 cubic yards of crushed concrete from the old foundations sits in the middle of the field and will be reused in the new stadium bowl.
Two small sections in the south end zone, the old baseball dugouts, are still standing because asbestos from the 1970s was found there.
Crews stopped work and notified the state Department of Health, and the sections will come down once a removal plan is approved.
What comes next
Expect a lull in visible work while plans for the new stadium are finalized.
Yadao said a groundbreaking ceremony is planned for the first quarter of 2027, calling it a symbolic start rather than the true start of construction.
The new stadium is still targeted to open in 2029.
Its size has not been settled, with 31,000 seats promised and developers hoping funding allows about 40,000 at opening.
The early demolition finish is not expected to move up the opening date, since agency and environmental reviews still have to be completed. |